Much was accomplished this week. Slabs were poured for Buildings C, D, E and F. Approximately 60,000 SF. Buildings C and E were poured in one day and the other two the following successive days. We also finished the perimeter footings for Buildings G and M. On the 13th we started installing the Cast in Place Bond Beams on the second level of Building A South Side around the Band Room. A very productive week with weather cooperating.