Tuesday, November 2, 2010

Waiting on the rain.

Part E up to the expansion joint has been graded and grade beams excavated. Vapor barrier has been installed on about half of the area.


Part D was supposed to be poured in the morning but a 70% chance of rain has pushed us back.



Part D ready for concrete.



Part C was supposed to be poured this morning but the 70% chance of rain held us up.