M1 East footings have been excavated, we are giving the plumber and electrican time to install their under footing utilities
Column footings on the north side of G are poured so the slab prep for F can continue.
Slab prep for section F. interior has been graded and vapor barrier is being installed.
East side of the expansion joint in part E and continuing into part F. Vapor barrier is going down as well as the rebar.
Vapor barrier in part E east of the expansion joint.
Prepping slab Friday morning.
Part D. due to 1 1/4'' rain on Wed. we are dewatering the prepared slab areas.
Dewatering part C.