Saturday, November 6, 2010

Update

M1 East footings have been excavated, we are giving the plumber and electrican time to install their under footing utilities
Column footings on the north side of G are poured so the slab prep for F can continue.


Slab prep for section F. interior has been graded and vapor barrier is being installed.


East side of the expansion joint in part E and continuing into part F. Vapor barrier is going down as well as the rebar.




Vapor barrier in part E east of the expansion joint.




Prepping slab Friday morning.






Part D. due to 1 1/4'' rain on Wed. we are dewatering the prepared slab areas.







Dewatering part C.