Week of November 15 thru November 20

This week started with 2 inches of rain so there was very little production on Monday and Tuesday. L Building layout was completed on Tuesday and the footings were started. The exterior footings for that building are complete as of the date of this posting with the pictures to follow. The first three pictures show the wall that the Cast in Place Bond Beams are being installed.