Friday, November 19, 2010

G Building Interior Footings

Layout of G Building Interior Footings as well as the instalaltion fo these footings has begun. We have ran into an issue with the plumber installing his pipes too shallow at column footing locations, that is being addressed and corrected.













L Building Footings

L Building Exterior Footing Package was completed yesterday. The layout, excavation, form, reinforce and pour took a total of three days.












Bond Beams

The installation of the Bond Beams for Building A will be completed this week. The rebar cage being installed include #8 bars top and bottom with #4 stirrups. Future Bond Beams will be installed with the use of scaffolding.
These beams will also have imbeds placed in them when they arrive on site.






























Thursday, November 18, 2010

Week of November 15 thru November 20

This week started with 2 inches of rain so there was very little production on Monday and Tuesday. L Building layout was completed on Tuesday and the footings were started. The exterior footings for that building are complete as of the date of this posting with the pictures to follow. The first three pictures show the wall that the Cast in Place Bond Beams are being installed.























Week of November 8 thru November 13

Much was accomplished this week. Slabs were poured for Buildings C, D, E and F. Approximately 60,000 SF. Buildings C and E were poured in one day and the other two the following successive days. We also finished the perimeter footings for Buildings G and M. On the 13th we started installing the Cast in Place Bond Beams on the second level of Building A South Side around the Band Room. A very productive week with weather cooperating.