We finalized the placement of more column steel and Wednesday we had a hard rain that saturated the site. We immediately worked on getting the water of the pads and have been able to continue to prep these slabs for an aggressive pour schedule starting 1/11.
We are pouring the first grouping of columns around noon today. Once those are poured all personnel will be split up accordingly to get four slabs ready. We also are waiting to prep the first upper deck slab as well but the deck has yet to be completed.