Friday, January 7, 2011

Work Update 1/7

We finalized the placement of more column steel and Wednesday we had a hard rain that saturated the site. We immediately worked on getting the water of the pads and have been able to continue to prep these slabs for an aggressive pour schedule starting 1/11.
We are pouring the first grouping of columns around noon today. Once those are poured all personnel will be split up accordingly to get four slabs ready. We also are waiting to prep the first upper deck slab as well but the deck has yet to be completed.














Wednesday, January 5, 2011

Work Update

Work on the site has been steady, highly productive and timely. As the pictures show we have completed the cast in place walls package for Building M. Building M's Gym floor slab prep is on schedule no that the pluming layout problems have been solved. Thsi would also include G that is also shown here. L and K interior work has now begun now that the exterior footing package for both of those buildings is completed. J has also started.














Tuesday, December 21, 2010

The work over the last two weeks have been very productive. Along with the placement of the Cast in Place Columns the perimeter footing package for building K has been completed. The footings at the west end of K had some trouble being installed because of water seeping from the sand pile for Building J. The sitre has had problems with the soli conditions around us but luckily we have had very little incidents with the overall footing placement. Also the Cast in Place Walls for M building are being placed as well. Vapor Barrier for G Building and M Building are also being done today.



















Wednesday, December 15, 2010

Update on Work Performed







































































































The project is advancing in three areas. The exterior footing package for Building K has commenced as of 12/14. We have placed a number of column footings for the elevated walkway cast in place columns as well as the continuous footings for the stairs. This is located between Buildings A and H in the courtyard. The instalaltion fo these will allow for the brick placement to commence at that location.
The Cast in Place Bond Beams for Building A have been completed and this has allowed for the second deck to be installed for that building ass well as Building B. We are scheduiled to pour that part of the second deck January 7.

M Building's footing package is complete. We have installaed the column footings for the entrance way for M as well. We have been waiting on the plumber to complete the work in M in order to prep the first slab for that building. We are scheduled for the first Building M pour January 5. M will be completed the following week.
G building's exterior and interuior footing package has been completed. We are waiting on the approval of the kitchen shop drawings so we can finish prepping that slab. That pour is scheduled for January 6.

Also did a walk through and took pictures of previously installed areas including a majority of the slabs.

The Cast in Place Columns located at A will be set and poured over the next couple of days.