Area D slab is being prepped for an early morning pour on Wednesday.
.JPG)
Slab D prep

Area C is being prepped for an early morning pour on Tuesday morning.

Area B has cured for 7 days and the curing blankets are being pulled off. Layout for CMU starts tomorrow by the mason.

Area A, CMU progression