Friday, September 10, 2010

September 10 - Footing bld A & B front of building

Work performed this date included continued set up of A building exterior grade beams moving in to B building.  Also tieing up the last of the exterior grade beams on the south side until the rest of the southside of the building beccomes available on Monday.

Passed all inspections and pouring approximately 235 LF of exterior grade beams this afternoon.  Almost th eexact smae amount as the first pour.

After a coordination discussion between myself, Brian Fallin and our superintendent it is jointly decided that we do no further digging until Monday in order to protect us form having to do any demucking due to the chance of rain on Sunday.  Saturday's agenda will be further layout and further preparation of rebar for B building.