The work over the last two weeks have been very productive. Along with the placement of the Cast in Place Columns the perimeter footing package for building K has been completed. The footings at the west end of K had some trouble being installed because of water seeping from the sand pile for Building J. The sitre has had problems with the soli conditions around us but luckily we have had very little incidents with the overall footing placement. Also the Cast in Place Walls for M building are being placed as well. Vapor Barrier for G Building and M Building are also being done today.
McClure Design & Build Contractors - Doing all Concrete Labor work for a 380,000 sq. ft High School
Tuesday, December 21, 2010
Wednesday, December 15, 2010
Update on Work Performed
The project is advancing in three areas. The exterior footing package for Building K has commenced as of 12/14. We have placed a number of column footings for the elevated walkway cast in place columns as well as the continuous footings for the stairs. This is located between Buildings A and H in the courtyard. The instalaltion fo these will allow for the brick placement to commence at that location.
The Cast in Place Bond Beams for Building A have been completed and this has allowed for the second deck to be installed for that building ass well as Building B. We are scheduiled to pour that part of the second deck January 7.
M Building's footing package is complete. We have installaed the column footings for the entrance way for M as well. We have been waiting on the plumber to complete the work in M in order to prep the first slab for that building. We are scheduled for the first Building M pour January 5. M will be completed the following week.
G building's exterior and interuior footing package has been completed. We are waiting on the approval of the kitchen shop drawings so we can finish prepping that slab. That pour is scheduled for January 6.
Also did a walk through and took pictures of previously installed areas including a majority of the slabs.
The Cast in Place Columns located at A will be set and poured over the next couple of days.