Thursday, September 16, 2010

Pictures from Wednesday, September 15, 2010

Footers into Building "C" continue as well as pour happened today which completed the north side of building "B".  Schedule to pour north side of building "C" footers tomorrow.


Rebar in south side of building "A" installed per submittal from rebar company, but they were not correct based on the plan.  White-Spunner is working with rebar company to remedy this issue, but McClure will have to remove dowels and reinstall new dowels.  Change Order is being generated to submit to White-Spunner.


McClure also delivered a 500 gallon diesel tank for refueling onsite equipment.