McClure Design & Build Contractors - Doing all Concrete Labor work for a 380,000 sq. ft High School
Thursday, September 30, 2010
Friday, September 24, 2010
September 23, Prepped piers footings in building C
Continued digging footings on Building D and prepped building C pier footings.
Wednesday, September 22, 2010
Poured front of C and part of D North Side
Finished prepping North side of Building C with rebar and dug and prepared part of building D and poured these locations today.
Four additional people will mobilize to job site tonight ready for work in the morning.
Four additional people will mobilize to job site tonight ready for work in the morning.
Tuesday, September 21, 2010
September 21, Building C continuing and Rebar on site
Rebar for building "C" arrived today. Off loading materials and continuing footing excavation on Building C and moving into D.
Site Visit Monday, September 20
Ross went to job site scheduling meeting today. Site looks clean and footings have been verified by surveying company that we are looking good.
Waiting on rebar, which should be here Tuesday, September 21.
Thursday, September 16, 2010
Pictures from Wednesday, September 15, 2010
Footers into Building "C" continue as well as pour happened today which completed the north side of building "B". Schedule to pour north side of building "C" footers tomorrow.
Rebar in south side of building "A" installed per submittal from rebar company, but they were not correct based on the plan. White-Spunner is working with rebar company to remedy this issue, but McClure will have to remove dowels and reinstall new dowels. Change Order is being generated to submit to White-Spunner.
McClure also delivered a 500 gallon diesel tank for refueling onsite equipment.
Rebar in south side of building "A" installed per submittal from rebar company, but they were not correct based on the plan. White-Spunner is working with rebar company to remedy this issue, but McClure will have to remove dowels and reinstall new dowels. Change Order is being generated to submit to White-Spunner.
McClure also delivered a 500 gallon diesel tank for refueling onsite equipment.
Wednesday, September 15, 2010
Saturday, September 11, 2010
Friday, September 10, 2010
September 10 - Footing bld A & B front of building
Work performed this date included continued set up of A building exterior grade beams moving in to B building. Also tieing up the last of the exterior grade beams on the south side until the rest of the southside of the building beccomes available on Monday.
Passed all inspections and pouring approximately 235 LF of exterior grade beams this afternoon. Almost th eexact smae amount as the first pour.
After a coordination discussion between myself, Brian Fallin and our superintendent it is jointly decided that we do no further digging until Monday in order to protect us form having to do any demucking due to the chance of rain on Sunday. Saturday's agenda will be further layout and further preparation of rebar for B building.
Wednesday, September 8, 2010
Subscribe to:
Posts (Atom)