Wednesday, October 20, 2010

Monday, October 18, 2010

B Slab Prep







Vapor barrier is down and rebar is being set in the interior footings.

Friday, October 15, 2010

B Slab Prep




While one crew preps B pad the other crew ties the rebar for the interior footings.

Thursday, October 14, 2010

A. Slab Curing


Concrete has been poured, finished, control lines cut and curing blankets placed.

Wednesday, October 13, 2010

Tuesday, October 12, 2010