Thursday, October 7, 2010

B-F


Underground plumbing and electrical installation in B thur F.

A. Slab Prep







Interior footings for part A are excavated. We need to backfill a bit more around the CMU walls then have the termite treatment applied before we start installing the vapor barrier.