Thursday, October 7, 2010

B-F


Underground plumbing and electrical installation in B thur F.

A. Slab Prep







Interior footings for part A are excavated. We need to backfill a bit more around the CMU walls then have the termite treatment applied before we start installing the vapor barrier.

CMUs Filled


The masons filled the CMU blocks yesterday, we are now backfilling and compacting around the blocks to continue our slap prep for building A.

Tuesday, October 5, 2010

Slab Prep


Slab of area A is being prepped for vapor barrier.

Concrete poured







East end of part F, and south side of part D exterior footings poured today.

Building A slab


The plumber and electrician are finishing up their under slab work for building A. The block should be filled today and we will start to prep the slab for a pour early next week.

Elevatr Pit







The elevatot pit walls have been poured and the forms have been stripped.