Friday, October 29, 2010

Building Update

Area D slab is being prepped for an early morning pour on Wednesday.
Slab D prep

Area C is being prepped for an early morning pour on Tuesday morning.


Area B has cured for 7 days and the curing blankets are being pulled off. Layout for CMU starts tomorrow by the mason.



Area A, CMU progression



















Wednesday, October 27, 2010

C. Slab Prep




Part C slap prep continues.

G. West Footer




Exterior footer on the west side of part G was poured today, as well as 3 column footers in part E.

Tuesday, October 26, 2010

G. West Footer


G west exterior footer is being excavated. The plumber and electrican will install their sleeves then we will add rebar and concrete.

Part C slab prep




Part C interior footers have been excavated and the termite treatment has been applied. Next step - Vapor Barrier

G. East exterior footer







Part G east and south part F, exterior footer were poured Friday afteroon.

Monday, October 25, 2010

F&G Footings











Southeast side of part F and the east side of part G footings prepped for concrete

Monday, October 18, 2010

B Slab Prep







Vapor barrier is down and rebar is being set in the interior footings.

Friday, October 15, 2010

B Slab Prep




While one crew preps B pad the other crew ties the rebar for the interior footings.

Thursday, October 14, 2010

A. Slab Curing


Concrete has been poured, finished, control lines cut and curing blankets placed.

Wednesday, October 13, 2010

Thursday, October 7, 2010

B-F


Underground plumbing and electrical installation in B thur F.

A. Slab Prep







Interior footings for part A are excavated. We need to backfill a bit more around the CMU walls then have the termite treatment applied before we start installing the vapor barrier.