McClure Design & Build Contractors - Doing all Concrete Labor work for a 380,000 sq. ft High School
Monday, August 30, 2010
Rain
Pad is soaked. There was over 3-4" of rain over the weekend. Survey points will be marked today. Pad must dry out before we start digging footings.
Thursday, August 26, 2010
August 25, 2010 - Working on Rebar package for Building A
Rebar on site for Building A
Rebar being fabricated.
Tying Rebar for Building A
Forming Materials on site.
Site plan table created.